Hiring a Contractor in Colorado: Contracts, Liens, and Defects
By Attorney Charles E. Liken Jr. What to put in the contract, how payments and mechanics’ liens interact, what to do if a lien is filed, and the deadlines for defect claims.
Charles E. Liken Jr., Esq. — On the Legal Front Lines · Former Government Investigator, Denver Human Services · Licensed Colorado Attorney · 20+ Years in Private Practice · Former Colorado Deputy District Attorney · Colorado Court-Rostered Child and Family Investigator · Former Colorado Real Estate Broker
Hiring a contractor for a remodel, a roof, a deck, or a new build is one of the larger contracts most households sign. Most jobs go fine. When they do not, the problems tend to be the same: a vague contract, payments that got ahead of the work, a subcontractor who was not paid and files a lien on your home, or a defect that shows up after the contractor is gone. This guide covers the Colorado rules that matter at each stage and the deadlines to calendar. It is general information and not a substitute for a lawyer’s review of your contract.
Before you sign
- Get a written contract that states the scope in detail, the total price, the start and finish dates, and who pulls the permits.
- Tie payments to completed stages of work, not to the calendar, and avoid paying the full price before work begins.
- Require change orders in writing, with the price and the schedule effect, before the extra work starts.
- Ask for proof of liability insurance and for the contractor’s city or county license or registration where one is required. Check with the building department.
- Ask for the names of subcontractors and suppliers, and for lien waivers as each is paid.
- Ask who warrants the work, for how long, and what you must do to make a claim.
- Get two or three bids and call references from recent jobs of the same kind.
Payments and the lien law
Colorado’s mechanics’ lien law lets people who furnish labor, equipment, or materials to improve real property claim a lien on that property, even when the person who hired them was the contractor and not you (C.R.S. § 38-22-101(1)). That is why paying a contractor does not by itself keep a lien off your property if the contractor does not pay the subcontractors. The statute expects the contract price to be payable in installments or on completion, with a share payable at least thirty-five days after final completion, starting with fifteen percent of the first $250,000 of the price and smaller percentages above that, and it says a payment made before it is due under the contract does not defeat others’ lien rights (C.R.S. § 38-22-102(1) and (2)). For an existing single-family home, or a single-family home you own and live in or are building to live in, there is an important protection: it is an affirmative defense to a suit to enforce a lien that you, or someone acting for you, paid the contractor or a subcontractor what the contract and the law require, including change orders, for the purpose of paying the subcontractors and suppliers (C.R.S. § 38-22-102(3.5) and C.R.S. § 38-22-113(4)). You must raise the defense in court, and it does not cover every kind of property, so keep a record of every payment and ask for lien waivers as each person is paid. A lien waiver is not binding on third parties, and a waiver of lien rights must include a statement that the waiving party’s debts to third parties for the same goods or services have been paid or will be timely paid (C.R.S. § 38-22-119). When a city or county issues a building permit for work on residential property (other than new residential construction or a building with more than four units), it must mail a notice of the lien law to the property (C.R.S. § 38-22-105.5). A principal contractor can avoid liens on a project by posting performance and payment bonds, each for 150 percent of the contract price, before work starts (C.R.S. § 38-22-129).
If a lien is filed against your home
A lien claimant must file a sworn lien statement with the county clerk and recorder. To preserve the lien, a notice of intent to file must be served on the owner and the prime contractor at least ten days before filing. The statement must generally be filed within four months after the last labor or materials, or within two months after completion for people who supplied only day or piece labor (C.R.S. § 38-22-109). A lien does not hold the property beyond six months after the last work unless a suit to enforce it is started and a notice of the suit is recorded within that time (C.R.S. § 38-22-110). Once the claim is paid, the claimant must record a satisfaction within ten days after a written request, or owe $10 per day (C.R.S. § 38-22-118). Someone who files a lien for more than is due, knowing it, can forfeit the lien and owe the owner’s costs and attorney fees, and the statute was amended in 2026 to spell out what counts as an amount “due” (C.R.S. § 38-22-128).
Contractor and lien dates
Fill in whichever dates you have. Each one produces a date or two to calendar. Nothing you type leaves this page.
If the work is defective
Construction-defect claims against builders and contractors follow a process before a lawsuit. A homeowner generally must send a written notice of claim by certified mail or personal service at least 75 days before filing, or 90 days for commercial property. In any case, protect the property from further damage while you wait. For claims against a builder that joined the state’s multifamily construction incentive program (a program for attached housing of two or more units that began in 2026), the statute requires reasonable action to prevent further damage before filing. The contractor may ask to inspect, which must happen within thirty days of the notice. Then the contractor may offer to pay a sum or to remedy the defect, and it must share certain plans, reports, and insurance information with the claimant (C.R.S. § 13-20-803.5). The time limit is the two years in the general statute, counted from when you discovered or should have discovered the physical signs of the defect, and in no case more than six years after substantial completion, except that a claim arising in the fifth or sixth year can be brought within two years (C.R.S. § 13-80-104). If you send the notice of claim before the time limit runs out, the limit is tolled until 60 days after the notice-of-claim process ends (C.R.S. § 13-20-805(1)). Take photographs, keep the contract and every change order, and write down the dates.
Smaller disputes
For a dispute over a smaller amount, our small claims guide explains the court. If you need help finding a lawyer or legal aid, see our directory of free and low-cost legal help. The civil litigation page describes how we help with contract disputes.
Ready when you are — talk it through with Attorney Liken.
Start here: a no-charge 20-minute phone call directly with Attorney Liken.
Frequently asked questions
Can a subcontractor put a lien on my home if I paid the contractor?
Yes, a lien can be filed. The mechanics’ lien law gives people who furnish labor or materials a lien on the property even when the contractor hired them (C.R.S. § 38-22-101). For an existing single-family home, or a single-family home you own and live in or are building to live in, it is an affirmative defense to a suit to enforce the lien that you paid the contractor or a subcontractor what the contract and the law require, including change orders, for the purpose of paying the subcontractors and suppliers (C.R.S. §§ 38-22-102(3.5), 38-22-113(4)). You must raise it, and it does not cover every property. For other property, a payment made before it was due under the contract generally does not defeat others’ lien rights (C.R.S. § 38-22-102(2)).
How long does a contractor have to file a lien in Colorado?
Generally within four months after the last labor or materials, with a notice of intent served at least ten days before filing, and a suit to enforce within six months after the last work (C.R.S. §§ 38-22-109, 38-22-110).
What is a notice of claim for a construction defect?
A written notice a homeowner must send at least 75 days before filing a defect lawsuit, or 90 days for commercial property, by certified mail or personal service (C.R.S. § 13-20-803.5).
How long do I have to sue a contractor over defective work?
Generally two years from when you discovered or should have discovered the defect, and no more than six years after substantial completion, with an extension for claims arising in years five or six (C.R.S. § 13-80-104). Sending a notice of claim before the time limit runs out tolls it until 60 days after the notice-of-claim process ends (C.R.S. § 13-20-805).